Fiber Optic Center has a team of technical experts and marketing strategists with decades of years in the field. This team contributes to the fiber, cable and specialty industries coverage through news, alerts, reports and general media information.
QUESTION: Why is automation so difficult for fiber optic assembly houses?
ANSWER:
Automation is difficult because there’s a lack of standardization, and we’re not even speaking about standardization in one particular connector style. ...
QUESTION: How can one ensure maximum life and performance of the fiber optic polishing fixture? ANSWER: Following up the ultrasonic cleaning with brushing of the ferrule bores and blowing dry with clean, compressed air will help to ensure maximum life
...
QUESTION: When testing for traffic with a fiber identifier on a bidirectional fiber does the fiber identifier show traffic both ways?
ANSWER:
When testing for traffic with a fiber identifier on a bidirectional fiber, a fiber identifier can indicate the...
QUESTION: Do you have feedback from actual Phenix fibersect customers on their real experiences with this cleaving option?
ANSWER:
Here’s what a few Phenix fibersect customers have confirmed:
Customer A: “The people on our assembly line...
QUESTION: What documentation have you published on how operators can better meet design goals?
ANSWER:
We have a full article blog, Critical Design Goals to Manufacture Optical Fiber Preforms, that can be found...
QUESTION:
We are experiencing chemical level changes in our gas delivery system bubbling process. You have staff that consults on this?
ANSWER:
We do. The bubbling process is critical, and it is important that the gas flow and liquid reagent temperature...
QUESTION:
We manufacture specialty optical preforms and fibers and are looking for solutions to our strength and deposition issues.
Can you help with that challenge?
ANSWER:
Fiber Optic Center does offer preform fabrication consulting services to...
QUESTION:
We are experiencing chemical level drops in our chemical bubbler. Is this a temperature issue or should we be focusing on other variables?
ANSWER:
Once the chemical bubblers are at proper levels and stable temperature the vapor deposition can...
QUESTION: What are the considerations for cleaning fluids being transported?
ANSWER:
Considerations for cleaning fluids being transported:
Air Shipment Requirements
HAZMAT Restrictions
Spill and Leak Concerns
ADDITIONAL CONTENT...
QUESTION:
We are having issues with shrinkage and are focusing on the polish step. Looking for some steps, best practices, solutions, etc.
ANSWER:
The final step prior to the first deposition pass is a high-temperature (~2000 degrees C) flame polish....